Precautions for installation of spray tower

2020-10-09 875

The spray tower is also called the spray tower. The main equipment is not packed in the tower, maybe the tray, but it has set up the absorber with nozzle. Then the liquid enters into the tower through the top of the tower. In this process, the side needs to pass through the nozzle and spray into the mist or raindrop shape. Next, the gas will enter through the lower part of the tower and touch the liquid in the form of mist or raindrop for mass transfer, so that the relatively simple soluble components of the gas can be absorbed. The final spray tower has the advantages of simple structure, small resistance and convenient operation and repair. So, what should be paid attention to when spraying tower is installed? Next, Jiangmen Guoqi environmental protection editor will give you a brief introduction!

1. In the construction, it is necessary to do a good job in processing and save steel pipes as much as possible. Because the spacing above the nozzle is usually 3.2-3.6 meters, but because the steel pipe is set at 6 meters, we need to plan the amount of steel pipe used, so that enterprises can be useful. In addition, it is necessary to mark the pipe when processing, so that time will be saved in the installation.

2. In the process of pipeline processing, it is required to arrange personnel first

江门国齐环保

The support and hanger on the pipe can be installed directly after processing. After the installation, the main pipeline needs to be installed first, so it is suggested to connect the main pipeline after the ground assembly is completed. This saves labor.

3. Pay attention to the reliability of working at height and using electricity. It is not only necessary to prevent the damage caused by the machinery, but also to pay attention to the length and shape of the groove when pressing groove, so as to prevent water leakage caused by unqualified processing. Together, we also need to pay attention to the quality of screw thread. It is suggested that the pipeline pressure test should be carried out after the pipe network installation is completed to ensure that the pipe network does not leak.

4. When cooperating with other special construction, the products must be carefully maintained, especially when decorating the suspended ceiling, the position of the spray head must be reserved for holes, and it is recommended not to miss the installation of spray head.

After the final system device is finished, the linkage experiment must be carried out to ensure the normal operation of the system. In addition, the wet alarm valve device needs to be installed according to the instruction manual, so as to prevent errors on the device.